Map of 298 permits within a quarter mile of 441 Stuart StElectrical, 1 Huntington Av, Oct 2, 2026Alteration or repair, 116 Commonwealth Av, Oct 1, 2026Alteration or repair, 200 Clarendon St, Sep 30, 2026Alteration or repair, 176 Commonwealth Av, Sep 30, 2026Roofing, 126 Commonwealth Av, Sep 30, 2026Electrical, 131 Dartmouth St, Sep 30, 2026Electrical, 71 Appleton St, Sep 30, 2026Electrical, 93-95 Newbury St, Sep 30, 2026Alteration or repair, 125 Newbury St, Sep 30, 2026Alteration or repair, 62 Clarendon St, Sep 29, 2026Electrical, 1 Huntington Av, Sep 29, 2026Alteration or repair, 190-200 Berkeley St, Sep 29, 2026Sign, 125 Newbury St, Sep 29, 2026Alteration or repair, 222 Berkeley St, Sep 28, 2026Plumbing, 500 Boylston St, Sep 28, 2026Electrical, 90 Commonwealth Av, Sep 28, 2026Plumbing, 154-170 Commonwealth Av, Sep 25, 2026Plumbing, 116 Huntington Av, Sep 25, 2026Plumbing, 116 Huntington Av, Sep 25, 2026Electrical, 116 Huntington Av, Sep 25, 2026Electrical, 116 Huntington Av, Sep 25, 2026Plumbing, 197 Clarendon St, Sep 24, 2026Plumbing, 176 Commonwealth Av, Sep 24, 2026Fire systems, 200 Clarendon St, Sep 23, 2026Electrical, 190-200 Berkeley St, Sep 23, 2026Plumbing, 176 Commonwealth Av, Sep 22, 2026Electrical, 176 Commonwealth Av, Sep 22, 2026Fire systems, 176 Commonwealth Av, Sep 22, 2026Electrical, 222 Berkeley St, Sep 22, 2026Electrical, 176 Commonwealth Av, Sep 22, 2026Plumbing, 269-285 Columbus Av, Sep 21, 2026Plumbing, 269-285 Columbus Av, Sep 21, 2026Fire systems, 79 Newbury St, Sep 21, 2026Electrical, 190-200 Berkeley St, Sep 21, 2026Electrical, 197 Clarendon St, Sep 21, 2026Alteration or repair, 222 Berkeley St, Sep 19, 2026Alteration or repair, 116 Huntington Av, Sep 18, 2026Alteration or repair, 500 Boylston St, Sep 18, 2026Electrical, 100 Huntington Av, Sep 17, 2026Alteration or repair, 190-200 Berkeley St, Sep 16, 2026Electrical, 414-426 Boylston St, Sep 16, 2026Alteration or repair, 414-426 Boylston St, Sep 15, 2026Plumbing, 100 Huntington Av, Sep 15, 2026Electrical, 28 Exeter St, Sep 15, 2026Alteration or repair, 166 Newbury St, Sep 14, 2026Electrical, 116 Commonwealth Av, Sep 14, 2026Electrical, 126 Commonwealth Av, Sep 14, 2026Electrical, 126 Commonwealth Av, Sep 14, 2026Electrical, 79 Newbury St, Sep 11, 2026Electrical, 161 Newbury St, Sep 11, 2026Alteration or repair, 162 Newbury St, Sep 10, 2026Alteration or repair, 100 Huntington Av, Sep 10, 2026Electrical, 79 Newbury St, Sep 10, 2026Alteration or repair, 414-426 Boylston St, Sep 10, 2026Alteration or repair, 200 Clarendon St, Sep 9, 2026Alteration or repair, 1 Huntington Av, Sep 4, 2026Alteration or repair, 1 Huntington Av, Sep 4, 2026Electrical, 130 Commonwealth Av, Sep 4, 2026Electrical, 143 Newbury St, Sep 4, 2026Sign, 127-131 Clarendon St, Sep 4, 2026Plumbing, 116 Huntington Av, Sep 3, 2026Plumbing, 116 Huntington Av, Sep 3, 2026Electrical, 149 Newbury St, Sep 3, 2026Fire systems, 100 Huntington Av, Sep 3, 2026Electrical, 209 Columbus Av, Sep 3, 2026Alteration or repair, 209 Columbus Av, Sep 2, 2026Roofing, 500 Boylston St, Sep 2, 2026Fence, wall or deck, 81 Appleton St, Sep 2, 2026Electrical, 535-541 Boylston St, Sep 2, 2026Alteration or repair, 176 Commonwealth Av, Sep 1, 2026Electrical, 500 Boylston St, Sep 1, 2026Electrical, 560 Boylston St, Aug 28, 2026Electrical, 168 Newbury St, Aug 27, 2026Plumbing, 200 Clarendon St, Aug 26, 2026Plumbing, 10 Huntington Av, Aug 26, 2026Alteration or repair, 100 Huntington Av, Aug 26, 2026Electrical, 131 Dartmouth St, Aug 25, 2026Electrical, 157 Berkeley St, Aug 25, 2026Electrical, 157 Berkeley St, Aug 25, 2026Alteration or repair, 535-541 Boylston St, Aug 24, 2026Plumbing, 131 Dartmouth St, Aug 24, 2026Alteration or repair, 28 Exeter St, Aug 20, 2026Roofing, 217 W Canton St, Aug 20, 2026Plumbing, 100 Huntington Av, Aug 20, 2026Alteration or repair, 500 Boylston St, Aug 18, 2026Alteration or repair, 79 Newbury St, Aug 18, 2026Alteration or repair, 168 Newbury St, Aug 18, 2026Plumbing, 190-200 Berkeley St, Aug 18, 2026Electrical, 200 Clarendon St, Aug 18, 2026Electrical, 321-323 Columbus Av, Aug 18, 2026Electrical, 149 Newbury St, Aug 18, 2026Electrical, 131 Dartmouth St, Aug 18, 2026Alteration or repair, 535-541 Boylston St, Aug 17, 2026Alteration or repair, 174 Commonwealth Av, Aug 17, 2026Plumbing, 1 Huntington Av, Aug 17, 2026Electrical, 149 Newbury St, Aug 17, 2026Fire systems, 116 Huntington Av, Aug 17, 2026Electrical, 10 Huntington Av, Aug 17, 2026Electrical, 116 Huntington Av, Aug 17, 2026Electrical, 130 Commonwealth Av, Aug 17, 2026Alteration or repair, 426 Stuart St, Aug 17, 2026Alteration or repair, 157 Berkeley St, Aug 14, 2026Electrical, 560 Boylston St, Aug 14, 2026Electrical, 190-200 Berkeley St, Aug 13, 2026Fire systems, 190-200 Berkeley St, Aug 13, 2026Electrical, 190-200 Berkeley St, Aug 13, 2026Fire systems, 130 Commonwealth Av, Aug 12, 2026Electrical, 119-125 Chandler St, Aug 12, 2026Electrical, 119-125 Chandler St, Aug 12, 2026Electrical, 10 Huntington Av, Aug 12, 2026Electrical, 61 Chandler St, Aug 12, 2026Alteration or repair, 10 Huntington Av, Aug 11, 2026Mechanical (HVAC), 53 Clarendon St, Aug 11, 2026Electrical, 131 Dartmouth St, Aug 11, 2026Electrical, 53 Clarendon St, Aug 11, 2026Plumbing, 53 Clarendon St, Aug 10, 2026Plumbing, 53 Clarendon St, Aug 10, 2026Sign, 500 Boylston St, Aug 7, 2026Electrical, 200 Clarendon St, Aug 6, 2026Electrical, 1 Exeter Pz, Aug 6, 2026Sign, 414-426 Boylston St, Aug 6, 2026Alteration or repair, 35 Lawrence St, Aug 5, 2026Plumbing, 37 Lawrence St, Aug 5, 2026Plumbing, 37 Lawrence St, Aug 5, 2026Fire systems, 535-541 Boylston St, Aug 5, 2026Fire systems, 131 Dartmouth St, Aug 5, 2026Electrical, 535-541 Boylston St, Aug 5, 2026Electrical, 200 Clarendon St, Aug 5, 2026Sign, 501 Boylston St, Aug 5, 2026Fire systems, 165 Newbury St, Aug 4, 2026Plumbing, 535-541 Boylston St, Aug 3, 2026Plumbing, 535-541 Boylston St, Aug 3, 2026Plumbing, 535-541 Boylston St, Aug 3, 2026Plumbing, 159 Newbury St, Aug 3, 2026Electrical, 116 Huntington Av, Aug 3, 2026Plumbing, 27 Stanhope St, Jul 31, 2026Electrical, 200 Clarendon St, Jul 31, 2026Electrical, 190-200 Berkeley St, Jul 31, 2026Electrical, 265-275 Dartmouth St, Jul 31, 2026Roofing, 74 Chandler St, Jul 30, 2026Alteration or repair, 390-406 Stuart St, Jul 30, 2026Electrical, 426 Stuart St, Jul 30, 2026Sign, 10 Huntington Av, Jul 30, 2026Roofing, 83 Dartmouth St, Jul 29, 2026Alteration or repair, 10-20 Harcourt St, Jul 29, 2026Electrical, 222 Berkeley St, Jul 29, 2026Alteration or repair, 100 Huntington Av, Jul 29, 2026Sign, 119 Newbury St, Jul 29, 2026Plumbing, 174 Commonwealth Av, Jul 28, 2026Electrical, 414-426 Boylston St, Jul 27, 2026Fire systems, 500 Boylston St, Jul 27, 2026Alteration or repair, 200 Clarendon St, Jul 27, 2026Sign, 131 Dartmouth St, Jul 27, 2026Alteration or repair, 1 Exeter Pz, Jul 27, 2026Electrical, 200 Clarendon St, Jul 24, 2026Alteration or repair, 1 Huntington Av, Jul 23, 2026Alteration or repair, 426 Stuart St, Jul 23, 2026Fire systems, 165 Newbury St, Jul 23, 2026Electrical, 200 Clarendon St, Jul 23, 2026Electrical, 1 Huntington Av, Jul 23, 2026Alteration or repair, 130 Commonwealth Av, Jul 22, 2026Electrical, 290 Columbus Av, Jul 21, 2026Alteration or repair, 149 Newbury St, Jul 21, 2026Plumbing, 1 Huntington Av, Jul 20, 2026Alteration or repair, 154-170 Commonwealth Av, Jul 20, 2026Alteration or repair, 116 Huntington Av, Jul 20, 2026Electrical, 200 Clarendon St, Jul 17, 2026Fire systems, 269-285 Columbus Av, Jul 17, 2026Alteration or repair, 100 Huntington Av, Jul 17, 2026Alteration or repair, 500 Boylston St, Jul 16, 2026Electrical, 119 Berkeley St, Jul 16, 2026Electrical, 119 Berkeley St, Jul 16, 2026Electrical, 119 Berkeley St, Jul 16, 2026Sign, 287-293 Columbus Av, Jul 16, 2026Alteration or repair, 131 Dartmouth St, Jul 16, 2026Electrical, 560 Boylston St, Jul 15, 2026Alteration or repair, 265-275 Dartmouth St, Jul 14, 2026Plumbing, 265-275 Dartmouth St, Jul 14, 2026Plumbing, 77 Appleton St, Jul 14, 2026Alteration or repair, 1 Huntington Av, Jul 13, 2026Alteration or repair, 157-159 Newbury St, Jul 13, 2026Alteration or repair, 154-170 Commonwealth Av, Jul 10, 2026Electrical, 414-426 Boylston St, Jul 10, 2026Alteration or repair, 165 Newbury St, Jul 9, 2026Alteration or repair, 414-426 Boylston St, Jul 8, 2026Alteration or repair, 27 Stanhope St, Jul 8, 2026Alteration or repair, 1 Exeter Pz, Jul 8, 2026Electrical, 157-159 Newbury St, Jul 8, 2026Electrical, 157 Berkeley St, Jul 8, 2026Alteration or repair, 200 Clarendon St, Jul 7, 2026Plumbing, 7 Harcourt St, Jul 7, 2026Plumbing, 7 Harcourt St, Jul 7, 2026Electrical, 144 Commonwealth Av, Jul 7, 2026Electrical, 165 Newbury St, Jul 7, 2026Electrical, 265-275 Dartmouth St, Jul 7, 2026Electrical, 116 Commonwealth Av, Jul 7, 2026Alteration or repair, 190-200 Berkeley St, Jul 7, 2026Sign, 1 Huntington Av, Jul 7, 2026Alteration or repair, 116 Huntington Av, Jul 6, 2026Plumbing, 149 Newbury St, Jul 2, 2026Electrical, 131 Dartmouth St, Jul 2, 2026Alteration or repair, 40 Trinity Pl, Jul 1, 2026Alteration or repair, 200 Clarendon St, Jul 1, 2026Alteration or repair, 61 Chandler St, Jul 1, 2026Electrical, 131 Dartmouth St, Jul 1, 2026Electrical, 165 Newbury St, Jul 1, 2026Electrical, 119-125 Chandler St, Jul 1, 2026Fire systems, 501 Boylston St, Jul 1, 2026Alteration or repair, 119 Berkeley St, Jun 30, 2026Alteration or repair, 119 Berkeley St, Jun 30, 2026Alteration or repair, 119 Berkeley St, Jun 30, 2026Plumbing, 132 Newbury St, Jun 30, 2026Other, 560 Boylston St, Jun 29, 2026Fence, wall or deck, 74 Chandler St, Jun 29, 2026Alteration or repair, 76 Chandler St, Jun 29, 2026Plumbing, 40 Trinity Pl, Jun 29, 2026Electrical, 500 Boylston St, Jun 29, 2026Electrical, 40 Trinity Pl, Jun 29, 2026Alteration or repair, 131 Dartmouth St, Jun 26, 2026Plumbing, 119 Berkeley St, Jun 26, 2026Plumbing, 119 Berkeley St, Jun 26, 2026Plumbing, 119 Berkeley St, Jun 26, 2026Plumbing, 40 Trinity Pl, Jun 26, 2026Plumbing, 61 Chandler St, Jun 26, 2026Fire systems, 149 Newbury St, Jun 26, 2026Electrical, 131 Dartmouth St, Jun 26, 2026Alteration or repair, 61 Chandler St, Jun 25, 2026Plumbing, 61 Chandler St, Jun 25, 2026Plumbing, 269-285 Columbus Av, Jun 25, 2026Electrical, 144 Commonwealth Av, Jun 25, 2026Electrical, 144 Commonwealth Av, Jun 25, 2026Electrical, 149 Newbury St, Jun 25, 2026Sign, 160 Newbury St, Jun 25, 2026Electrical, 501 Boylston St, Jun 24, 2026Alteration or repair, 535-541 Boylston St, Jun 24, 2026Plumbing, 1 Huntington Av, Jun 22, 2026Plumbing, 116 Commonwealth Av, Jun 19, 2026Alteration or repair, 269-285 Columbus Av, Jun 18, 2026Alteration or repair, 77 Chandler St, Jun 18, 2026Plumbing, 85 Chandler St, Jun 18, 2026Fire systems, 1 Exeter Pz, Jun 18, 2026Sign, 125 Newbury St, Jun 18, 2026Plumbing, 130b-130 Newbury St, Jun 17, 2026Alteration or repair, 265-275 Dartmouth St, Jun 16, 2026Fire systems, 269-285 Columbus Av, Jun 16, 2026Electrical, 219-223 Columbus Av, Jun 16, 2026Electrical, 500 Boylston St, Jun 16, 2026Alteration or repair, 131 Dartmouth St, Jun 16, 2026Electrical, 1 Exeter Pz, Jun 15, 2026Electrical, 130b-130 Newbury St, Jun 15, 2026Electrical, 501 Boylston St, Jun 12, 2026Fire systems, 119 Newbury St, Jun 11, 2026Fire systems, 1 Exeter Pz, Jun 10, 2026Electrical, 119 Newbury St, Jun 10, 2026Electrical, 1 Exeter Pz, Jun 10, 2026Alteration or repair, 77 Appleton St, Jun 9, 2026Alteration or repair, 28 Exeter St, Jun 9, 2026Plumbing, 219-223 Columbus Av, Jun 9, 2026Plumbing, 219-223 Columbus Av, Jun 9, 2026Alteration or repair, 535-541 Boylston St, Jun 8, 2026Alteration or repair, 500 Boylston St, Jun 8, 2026Alteration or repair, 1 Huntington Av, Jun 8, 2026Alteration or repair, 125 Newbury St, Jun 8, 2026Plumbing, 269-285 Columbus Av, Jun 8, 2026Plumbing, 126 Commonwealth Av, Jun 8, 2026Electrical, 119 Newbury St, Jun 8, 2026Electrical, 390-406 Stuart St, Jun 5, 2026Alteration or repair, 96 Chandler St, Jun 5, 2026Electrical, 700 Boylston St, Jun 4, 2026Fire systems, 321-323 Columbus Av, Jun 4, 2026Roofing, 105 Appleton St, Jun 3, 2026Fire systems, 390-406 Stuart St, Jun 3, 2026Electrical, 130b-130 Newbury St, Jun 3, 2026Electrical, 535-541 Boylston St, Jun 3, 2026Electrical, 116 Huntington Av, Jun 3, 2026Electrical, 168 Newbury St, Jun 3, 2026Alteration or repair, 287-293 Columbus Av, Jun 2, 2026Alteration or repair, 119 Newbury St, Jun 2, 2026Plumbing, 154-170 Commonwealth Av, Jun 2, 2026Electrical, 500 Boylston St, Jun 2, 2026Fire systems, 131 Dartmouth St, Jun 2, 2026Other, 200 Clarendon St, Jun 1, 2026Alteration or repair, 200 Clarendon St, Jun 1, 2026Electrical, 770 Boylston St, Jun 1, 2026Alteration or repair, 321-323 Columbus Av, Jun 1, 2026Alteration or repair, 130b-130 Newbury St, May 29, 2026Plumbing, 321-323 Columbus Av, May 29, 2026Electrical, 200 Clarendon St, May 29, 2026Alteration or repair, 551 Boylston St, May 29, 2026Electrical, 560 Boylston St, May 28, 2026Electrical, 551 Boylston St, May 28, 2026Electrical, 116 Huntington Av, May 28, 2026Electrical, 100 Huntington Av, May 28, 2026Other, 390-406 Stuart St, May 27, 2026Plumbing, 157-159 Newbury St, May 27, 2026Plumbing, 149 Newbury St, May 27, 2026Plumbing, 551 Boylston St, May 27, 2026Plumbing, 157-159 Newbury St, May 27, 2026660 ft Map preview
Open mapBack to list
  • Searched address
  • Addition or alteration
  • Electrical, plumbing, HVAC
  • Roof, fence, sign, facade
  • Demolition
  • Paperwork or other

441 Stuart St

Boston, MA 02116

189 permits on record here. The newest, Aug 25: Replace 2 hot water storage tanks. Within a quarter mile, the city has issued 354 more permits since May 1.

MayJunJulAugSepOct
Here189 permits · 441 Stuart St
  1. Aug 25$50,000
  2. Aug 24$52,000
  3. Apr 3$15,000
  4. Mar 18$1,500
  5. Feb 19$130,750
  6. Feb 16$16,500
  7. Feb 9$8,500
  8. Dec 12, 2025$500
  9. Jul 25, 2025not listed
  10. May 30, 2025$1,000
  11. Mar 27, 2025$948,300
  12. Jul 22, 2024$594,300
  13. Jun 6, 2024$20,000
  14. May 30, 2024$20,000
  15. May 21, 2024$547,780
  16. May 14, 2024$120,000
  17. Feb 21, 2024$55,620
  18. Jan 9, 2024$32,689
  19. Oct 3, 2023not listed
  20. Sep 19, 2023$37,147
  21. Jul 6, 2023$9,500
  22. May 10, 2021$300
  23. Retrofit r
    Electrical
    Jan 19, 2021$800
  24. Nov 12, 2020$2,500
  25. Nov 5, 2020$600
  26. Nov 5, 2020$2,000
  27. Oct 22, 2020$57,420
  28. Jan 24, 2020$5,500
  29. Dec 4, 2019$319,500
  30. Nov 5, 2019$5,000
  31. May 23, 2019$126,435
  32. Jul 18, 2018$93,075
  33. Apr 4, 2018$6,500
  34. Denham Capital - 7th Floor
    Alteration or repair
    Feb 6, 2018$14,000
  35. Jan 12, 2018$60,000
  36. Sep 26, 2017$6,500
  37. Sep 25, 2017$7,000
  38. Aug 31, 2017$1,000
  39. Aug 7, 2017not listed
  40. Jul 25, 2017$20,000
  41. Jul 20, 2017$227,000
  42. May 25, 2017$1,500
  43. May 4, 2017$13,650
  44. Apr 28, 2017$2,000
  45. Apr 27, 2017$90,032
  46. Apr 12, 2017$16,000
  47. Jan 5, 2017$5,100
  48. Dec 21, 2016$8,000
  49. Dec 21, 2016$2,000
  50. Dec 19, 2016$30,000
  51. Dec 19, 2016$10,000
  52. Dec 16, 2016$12,000
  53. Dec 14, 2016$1,500
  54. Dec 13, 2016$474,820
  55. Dec 12, 2016$47,000
  56. Nov 18, 2016$5,000
  57. Nov 18, 2016$6,169
  58. Nov 17, 2016$1,025,500
  59. Nov 2, 2016$10,500
  60. Nov 2, 2016$2,500
  61. Nov 1, 2016$13,000
  62. New sink & heater × 2 permits
    Plumbing
    Sep 8, 2016 to Oct 27, 2016$20,000
  63. Oct 26, 2016$1,200
  64. Oct 20, 2016$13,000
  65. Oct 20, 2016$2,000
  66. Oct 18, 2016$6,600
  67. Oct 18, 2016$27,771
  68. Oct 18, 2016$12,250
  69. Bright Horizons - 1st Floor
    Alteration or repair
    Oct 18, 2016not listed
  70. Sep 23, 2016$1,500
  71. Sep 16, 2016$365,000
  72. Sep 16, 2016$109,600
  73. Sep 13, 2016$80,000
  74. Sep 7, 2016$500
  75. Aug 30, 2016$10,000
  76. Aug 26, 2016$20,000
  77. Aug 16, 2016$55,000
  78. Aug 16, 2016$350,000
  79. Aug 11, 2016$32,900
  80. Aug 11, 2016$7,400
  81. Aug 4, 2016$77,906
  82. Network wiring
    Electrical
    Aug 4, 2016$2,300
  83. Aug 1, 2016$336,204
  84. Aug 1, 2016$88,865
  85. Jul 25, 2016$2,600,000
  86. Jul 25, 2016$550,000
  87. Jul 21, 2016$4,800
  88. Jul 8, 2016$44,000
  89. Jul 1, 2016$1,500,000
  90. Jun 21, 2016$478,897
  91. Jun 14, 2016$13,000
  92. May 20, 2016$15,000
  93. May 20, 2016$90,000
  94. May 10, 2016not listed
  95. Apr 11, 2016$70,360
  96. Apr 7, 2016$7,900
  97. Mar 31, 2016$40,000
  98. Mar 17, 2016not listed
  99. Feb 26, 2016$8,000
  100. Feb 23, 2016$4,500
  101. Renovating partial 10th floor
    Alteration or repair
    Feb 23, 2016$52,000
  102. Feb 10, 2016$4,600
  103. Jan 27, 2016$429,817
  104. Jan 19, 2016$12,500
  105. Jan 13, 2016$87,000
  106. Dec 23, 2015$350
  107. Dec 10, 2015$8,000
  108. Dec 8, 2015$10,800
  109. Nov 23, 2015$6,500
  110. Nov 23, 2015$59,000
  111. Nov 6, 2015$365,563
  112. Nov 4, 2015$1,087
  113. Oct 14, 2015$87,000
  114. Oct 7, 2015$1,000
  115. Sep 23, 2015$5,000
  116. Sep 23, 2015$87,000
  117. Sep 22, 2015$3,500
  118. Sep 9, 2015$9,750
  119. Sep 3, 2015$393,594
  120. Aug 21, 2015$200
  121. Jul 29, 2015$2,400
  122. Jul 24, 2015$12,500
  123. 6Th floor - tenant fit up
    Alteration or repair
    Jul 24, 2015$130,000
  124. Apr 22, 2015$300,000
  125. Mar 31, 2015$2,000
  126. Mar 18, 2015not listed
  127. Mar 5, 2015$2,000
  128. Feb 26, 2015$18,000
  129. Feb 26, 2015$3,000
  130. Feb 26, 2015$20,000
  131. Feb 6, 2015$300,000
  132. Dec 12, 2014$1,000
  133. Dec 8, 2014$1,500
  134. Nov 17, 2014$37,000
  135. Nov 5, 2014$10,500
  136. Nov 3, 2014$4,000
  137. Oct 30, 2014$6,000
  138. Sep 30, 2014$15,000
  139. Sep 29, 2014$5,000
  140. Sep 17, 2014$6,000
  141. Sep 15, 2014$10,000
  142. Sep 9, 2014$150,000
  143. Sep 4, 2014$1,000
  144. Sep 3, 2014$400
  145. Aug 19, 2014$10,000
  146. Aug 14, 2014$1,252,000
  147. Aug 6, 2014not listed
  148. Jul 24, 2014$24,160
  149. Jun 2, 2014$27,200
  150. May 23, 2014$5,000
  151. May 20, 2014$25,000
  152. May 15, 2014$175,000
  153. May 9, 2014$18,330
  154. Omega Funds
    Alteration or repair
    May 1, 2014$400,000
  155. Apr 16, 2014$75,567
  156. Nov 18, 2013$200
  157. Nov 12, 2013$5,000
  158. Nov 12, 2013$35,000
  159. Nov 7, 2013$23,000
  160. Oct 31, 2013$12,000
  161. Oct 31, 2013$8,000
  162. 6th floor
    Electrical
    Oct 23, 2013$12,500
  163. Oct 22, 2013not listed
  164. Oct 15, 2013$5,000
  165. Oct 15, 2013$140,000
  166. Oct 11, 2013$120,000
  167. Oct 2, 2013$632,000
  168. Aug 20, 2013$475
  169. Jun 27, 2013$800
  170. Apr 29, 2013$3,000
  171. Apr 23, 2013$25,000
  172. Apr 8, 2013$100
  173. Mar 22, 2013$204,000
  174. Mar 22, 2013$13,000
  175. Mar 11, 2013$1,500
  176. Mar 5, 2013$50,000
  177. Mar 5, 2013$1,050,000
  178. Nov 6, 2012$8,700,000
  179. Oct 19, 2012$44,000
  180. Sep 20, 2012$4,750
  181. Sep 18, 2012$700
  182. Sep 14, 2012$32,000
  183. Sep 11, 2012$201,600
  184. Sep 10, 2012$21,000
  185. Aug 9, 2012$54,131
  186. Apr 23, 2010$1,198
  187. Feb 16, 2010$30,000
This block250 to 1,000 ft · 150 permits in 149 projects
  1. Audio video wiring
    1 Huntington Av · 570 ft W · Electrical
    Oct 2$1,500
  2. Sep 30$14,000
  3. FedEx remodel
    131 Dartmouth St · 760 ft S · Electrical
    Sep 30$3,500
  4. Sep 29not listed
  5. Sep 29$15,250
  6. Sep 28$50,000
  7. Sep 24$85,000
  8. Sep 23$4,500
  9. Sep 23$67,875
  10. Sep 21$2,500
  11. Sep 21$2,500
  12. Sep 21$47,250
  13. Sep 21$7,750
  14. Sep 18$530,000
  15. Sep 17$120,000
  16. Sep 16$491,499
  17. Sep 15$28,000
  18. Sep 14$3,714
  19. Sep 10$98,000
  20. Sep 10$400,000
  21. Bain - 40th floor Demo offices
    200 Clarendon St · 310 ft NE · Alteration or repair
    Sep 9$18,500,000
  22. Sep 4$1,600
  23. Full apartment renovation of Unit 904
    1 Huntington Av · 570 ft W · Alteration or repair
    Sep 4$121,100
  24. Sep 4$3,000
  25. Sep 3$99,000
  26. Sep 3$1,500
  27. Installation of 2 petition walls
    209 Columbus Av · 1,000 ft E · Alteration or repair
    Sep 2$22,150
  28. Sep 2$1,250,000
  29. Sep 2$20,000
  30. Sep 1$15,000
  31. Aug 28$1,000
  32. Aug 27$4,000
  33. Aug 26$4,100
  34. Kitchen sink
    10 Huntington Av · 360 ft W · Plumbing
    Aug 26$15,000
  35. Aug 26$142,000
  36. FedEx Office
    131 Dartmouth St · 760 ft S · Electrical
    Aug 25$5,500
  37. Aug 24$82,922
  38. Aug 24$19,000
  39. Install kitchen sink
    100 Huntington Av · 810 ft SW · Plumbing
    Aug 20$500
  40. Aug 18$15,000
  41. Lower Level Shop remodeling
    168 Newbury St · 980 ft NW · Alteration or repair
    Aug 18$55,000
  42. Aug 18$76,000
  43. Aug 18$130,000
  44. Aug 18$15,000
  45. Aug 18$51,000
  46. Aug 17$127,463
  47. Aug 17$20,000
  48. Aug 17$12,000
  49. Jul 23 to Aug 17$103,000
  50. Aug 14$500
  51. Aug 13$4,560
  52. Aug 13$100,000
  53. Aug 13$750,000
  54. Aug 12$48,000
  55. Existing Health club renovation
    10 Huntington Av · 360 ft W · Alteration or repair
    Aug 11$148,659
  56. Aug 11$6,954
  57. Aug 7$2,700
  58. Aug 6$7,500
  59. Aug 5$30,000
  60. Aug 5$9,500
  61. Aug 5$97,000
  62. Aug 5$10,000
  63. Aug 3$12,000
  64. Aug 3$8,000
  65. Aug 3$8,000
  66. Jul 31$3,500
  67. Jul 31$2,985
  68. Jul 31$58,100
  69. Jul 31$15,000
  70. Jul 30$3,481
  71. Jul 30$5,600
  72. Jul 30$6,854
  73. Jul 29$1,100,000
  74. Jul 27$250,000
  75. Jul 27$2,445,000
  76. Jul 27$6,175
  77. Jul 24$800
  78. Jul 23$845,760
  79. Jul 23$25,000
  80. Jul 23$10,000
  81. Jul 21$6,000
  82. Jul 20$22,000
  83. Jul 17$40,000
  84. Jul 17$29,400
  85. Jul 17$2,500,000
  86. Demo existing service equipment
    500 Boylston St · 890 ft NE · Alteration or repair
    Jul 16$8,000
  87. Jul 16$2,501
  88. Jul 16$402,177
  89. Jul 15$2,000
  90. Full bathroom remodeling
    265-275 Dartmouth St · 850 ft NW · Alteration or repair
    Jul 14$28,500
  91. Jul 14$5,000
  92. Jul 13$20,000
  93. Jul 8$38,700
  94. Jul 7$16,729
  95. Jul 7$9,500
  96. Jul 7$5,000,000
  97. Jul 7$9,466
  98. Jul 2$8,500
  99. Jul 1$271,013
  100. Jul 1$479,864
  101. Jul 1$48,000
  102. Jun 30$4,500
  103. Jun 29$4,531
  104. Jun 29$2,500
  105. Jun 29$43,800
  106. Jun 29$9,000
  107. Jun 26$150,000
  108. Jun 26$6,000
  109. Jun 26$15,000
  110. Jun 25$9,500
  111. Jun 25$10,786
  112. Jun 24$550,000
  113. Jun 22$15,000
  114. Jun 18$154,412
  115. Jun 17$1,200
  116. Jun 16$72,000
  117. Jun 16$5,000
  118. Jun 16$12,000
  119. Jun 16$25,000
  120. Jun 16$383,800
  121. Jun 15$20,000
  122. Jun 9$10,000
  123. Jun 9$1,000
  124. Jun 8$1,000
  125. Jun 8$185,000
  126. Jun 8$58,784
  127. Jun 8$6,675
  128. Jun 5$9,500
  129. Jun 4$1,000
  130. Jun 4$5,000
  131. Jun 3$5,617
  132. Jun 3$1,500
  133. Jun 3$500
  134. Jun 3$11,500
  135. 2nd floor existing bathrooms
    287-293 Columbus Av · 750 ft SE · Alteration or repair
    Jun 2$54,000
  136. Jun 2$800
  137. Jun 2$325,000
  138. Jun 1$3,850
  139. Jun 1$157,458
  140. Jun 1$497,127
  141. May 29$90,000
  142. May 29$20,000
  143. May 29$54,700
  144. May 29$800,000
  145. May 28$100
  146. May 28$2,000
  147. May 28$10,000
  148. May 27$9,000
  149. Retro fit out
    551 Boylston St · 770 ft N · Plumbing
    May 27$14,000
Within a quarter mile1,000 ft to ¼ mi · 148 permits in 146 projects
  1. Oct 1$20,000
  2. Interior renovation of unit 5
    176 Commonwealth Av · 0.24 mi NW · Alteration or repair
    Sep 30$100,000
  3. Replace roof
    126 Commonwealth Av · 0.22 mi N · Roofing
    Sep 30$78,100
  4. Sep 30$2,500
  5. Sep 30$1,500
  6. Sep 30$450,000
  7. Stoop restoration
    62 Clarendon St · 0.20 mi SE · Alteration or repair
    Sep 29$12,650
  8. Sep 29$7,743
  9. Sep 28$122,250
  10. Sep 28$18,230
  11. Sep 25$1,200
  12. Sep 25$54,900
  13. Sep 25$25,800
  14. Sep 25$45,899
  15. Sep 25$20,000
  16. Sep 24$3,000
  17. Sep 22$30,000
  18. Sep 22$500
  19. Sep 22$2,000
  20. Sep 22$45,000
  21. Sep 22$50,000
  22. Sep 21$1,500
  23. Sep 19$252,000
  24. Sep 18$410,282
  25. Sep 16$27,968
  26. Sep 15$103,821
  27. Unit 802 renovation
    28 Exeter St · 0.21 mi NW · Electrical
    Sep 15$16,000
  28. Sep 14$5,000
  29. Sep 14$2,500
  30. Sep 14$25,000
  31. Sep 11$5,000
  32. Sep 11$30,000
  33. Interior improvements
    79 Newbury St · 0.24 mi N · Electrical
    Sep 10$5,000
  34. Sep 10$495,743
  35. Sep 4$10,000
  36. Sep 4$15,000
  37. Sep 3$21,350
  38. Sep 3$57,400
  39. Sep 3$6,825
  40. Sep 2$15,000
  41. Interior renovation of top-level unit
    176 Commonwealth Av · 0.24 mi NW · Alteration or repair
    Sep 1$300,000
  42. Aug 25$600
  43. Aug 25$25,000
  44. Unit 802, Upgrade kitchen and bathroom
    28 Exeter St · 0.21 mi NW · Alteration or repair
    Aug 20$110,000
  45. Aug 20$22,000
  46. Aug 18$157,000
  47. Aug 18$5,900
  48. Aug 17$87,500
  49. Aug 17$5,850
  50. Aug 17$39,000
  51. Aug 17$199,000
  52. Aug 17$10,000
  53. Aug 14$102,000
  54. Aug 12$5,691
  55. Mini split install × 2 permits
    119-125 Chandler St · 0.19 mi SE · Electrical
    Aug 12$1,500
  56. Aug 12$1,000
  57. Aug 11$40,000
  58. Aug 11$4,000
  59. New laundry and bar sink
    53 Clarendon St · 0.21 mi SE · Plumbing
    Aug 10$9,500
  60. Gas to grill
    53 Clarendon St · 0.21 mi SE · Plumbing
    Aug 10$1,000
  61. Aug 6$5,400
  62. Aug 6$12,000
  63. Replacement of 6 windows
    35 Lawrence St · 0.23 mi SE · Alteration or repair
    Aug 5$4,500
  64. Aug 5$825
  65. Aug 5$325
  66. Aug 5$18,391
  67. Aug 4$6,425
  68. Aug 3$800
  69. Aug 3$800
  70. Jul 30$12,500
  71. Jul 29$19,000
  72. Jul 29$44,700
  73. Jul 29$15,000
  74. Jul 29$1,525
  75. Jul 28$7,000
  76. Jul 27$3,000
  77. Jul 27not listed
  78. Jul 23$6,425
  79. Jul 22$30,000
  80. Jul 21$800,000
  81. Jul 20$8,000
  82. Jul 20$463,297
  83. Jul 16$6,000
  84. Jul 16$6,000
  85. Jul 16$6,000
  86. Master bath renovation
    77 Appleton St · 0.25 mi SE · Plumbing
    Jul 14$6,500
  87. Jul 13$789,474
  88. Jul 10$197,503
  89. Jul 10$29,965
  90. Jul 9$100
  91. Jul 8$131,959
  92. Jul 8$64,300
  93. Jul 8$8,300
  94. Jul 8$70,000
  95. UNIT 30-301 WH Replacement × 2 permits
    7 Harcourt St · 0.23 mi SW · Plumbing
    Jul 7$2,000
  96. Jul 7$2,400
  97. Install 3 CAT 5 wires
    165 Newbury St · 0.21 mi NW · Electrical
    Jul 7$2,000
  98. Jul 7$6,000
  99. Jul 6$1,692,044
  100. Jul 2$83,000
  101. Jul 1$73,357
  102. Jul 1$1,000
  103. Jul 1$2,000
  104. Jul 1$9,750
  105. Jun 30$27,931
  106. Jun 30$27,931
  107. Jun 30$31,931
  108. Jun 29$37,774
  109. Jun 29$60,000
  110. Jun 26$2,000
  111. Jun 26$2,000
  112. Jun 26$2,000
  113. Replace gas stove
    61 Chandler St · 0.25 mi SE · Plumbing
    Jun 26$2,800
  114. Jun 26$10,000
  115. Jun 25$11,171
  116. Jun 25$2,800
  117. Jun 25$23,106
  118. Jun 25$16,593
  119. Jun 25$147,125
  120. Jun 24$2,500
  121. Jun 19$5,500
  122. Jun 18$142,800
  123. Jun 18$40,000
  124. Jun 18$12,000
  125. Jun 18$7,743
  126. Jun 15$25,000
  127. Jun 12$3,000
  128. Jun 11$3,000
  129. Jun 10$6,000
  130. Jun 10$8,000
  131. Jun 10$37,000
  132. Renovation of bathroom removal of Tub
    77 Appleton St · 0.25 mi SE · Alteration or repair
    Jun 9$41,100
  133. Jun 9$230
  134. Jun 8$450,000
  135. Jun 8$6,000
  136. Jun 8$10,000
  137. Landmark Commission approvals attached
    96 Chandler St · 0.23 mi SE · Alteration or repair
    Jun 5$63,900
  138. Jun 3$20,000
  139. Jun 3$30,000
  140. Jun 2$296,246
  141. Jun 2$1,500
  142. Jun 1$15,000
  143. May 28$12,998
  144. May 27$17,000
  145. May 27$34,000
  146. May 27$3,000

This list shows the newest 300 of 354 permits. Pick a smaller circle or a later date to see the rest.

Boston Inspectional Services Department updated its data Oct 2, 2026. We checked it Oct 3, 07:50 UTC. Official data.

At this address: every permit the city holds. Nearby: permits from the last two years, from our copy of the city's data.

For agents and scripts: This page as Markdown · JSON · Nearby as JSON · MCP tool permits_near