11202 E Germann Rd, Mesa has 154 building permits on record. The most recent, opened Mar 16, 2026, is for other: Zf afp annual facilities permit for zf passive safety systems US inc for year 2026

All permits at this address

All permits at 11202 E Germann Rd
DateTypeWorkCost
Other
Zf afp annual facilities permit for zf passive safety systems US inc for year 2026
–
Plumbing
The proposed improvements include approximately 3,531 linear feet of new 12-inch sanitary sewer and 40 linear feet of 8-inch sanitary sewer pipe. These improvements will connect…
–
Other
Annual facilities permit (mother permit) for trw for year 2018
–
Electrical
AFP - B15 / Areas K & Q Equipment Relocation project, TRW Site II The scope of work is as follows: Area 'Q'. Remove existing x-ray machine and steel guardrail system. Relocate…
–
Electrical
AFP- Bldg. 2 Warehouse tenant improvements project for TRW / Site II. The scope of work is as follows: Remove and replace an exist. chiller unit w/ modifications to the exist…
–
Electrical
AFP: Bldg. 16 / ESF Relocation project for TRW / Site II. The project scope involves relocating existing environmental services operations from Bldg. 15-8 (previously permitted…
–
Alteration or repair
Pbi - permit to install new "ignition unit pre assembly line" with h-2/iib blast chimeny and 20 paf lexan shielding. No modification to the fire protection systems.
–
Fire systems
Addenda to bld2017-00977 - adding some addtional fire alarm devices to the original scope of work for m-bay. 3 Heat detectors, 1 pull station, 1 horn strobe and 1 relay module.
–
Fire systems
Refbld2016-08163 furnish & install 2 uv/ir flame detectors onto existing early warning control panel connected to existing fire alarm system.
–
Fire systems
Addenda (ref bld2016-06884) to replace existing fire alarm panel with a new notifier nfs2-640 fire alarm panel. Also replacing the existing monitoring modules with new monitor…
–
Alteration or repair
Permit to repair and replace existing laser welder with newer model. Connect to existing exhaust, modify as needed
–
Mechanical (HVAC)
No new square footage or utilities. Installation of di-10 inflator line-exist mechanical, electric services and hazardous material. Quantities to be modified as required. Deferred…
–
Fire systems
Deferred fire sprinklers. In-rack sprinklers. Ref bld2016-02216. Fees paid on main.
–
Fire systems
Replace existing fire alarm panel with a new notifier nfs2-640 fire alarm panel. Also replacing the existing monitoring modules with new monitor modules. Demoing devices in…
–
Electrical
AFP...B15/A Dust Collector Installation project for TRW Site II. The scope of work is as follows: Removal of the existing exterior vacuum pump with concrete pad. and shade cover…
–
Fire systems
AFP -Remove an existing hollow metal door and install a new double hollow metal door Bldg. 15 / Area "P2" - Existing structural cross-bracing will be modified to accommodate the…
–
Alteration or repair
Removal of the existing shi-2 inflator assembly line, existing steel equipment platform and assoc. Support equipment. Installation of new "sp12-evo" inflator assembly line #301 &…
–
Fire systems
AFP: Building 15 "B" Igniter #307. Installation ignition unit pre-assembly install #307. Modify existing mechanical and electrical systems. Fire supression and fire alarm to…
–
Alteration or repair
Scope of work includes demo of existing office space; reconfiguration of existing assembly equipment; installation of roi assembly equipment previously installed in b15/q (com#…
–
Alteration or repair
Combine an existing training room and conference room to make one large office area, redesignation of areas within b2 warehouse to facilitate the relocation of shipping/receiving…
–
Electrical
AFP: Removal of Existing "Finish Lines 'A' & 'C'" and existing "ROI Lines 3 & 4" with assoc. support equipment. Relocate Existing Helium Leak Check Lines 197/198 with assoc…
–
Roofing
AFP/ Building 15/ area "M" Load room improvements. Add to existing Lexan barrier. Install new 3 hour door Install new 3/4 hour exit door. Add 3 hour fire shutters. Install roof…
–
Electrical
AFP/ Building 15 area 'B" installation ignition unit pre-assembly install with blast chimney. Install 20 PSF rated Lexan shielding. Relocation of existing igniter sub-assembly…
–
Addition
Expansion of the exist. Compressor shed and install additional compressor - modify exist. Mech., elect., and piping systems. The expansion of the existing building 15/area "p" hp…
–
Electrical
AFP-Relocate existing CT scanner from B15/G to B15/I. Minor modification of existing electrical systems required
–
Electrical
AFP-Demoltion of existing conference room. Installation of 3 new modular ststems cubicles. Minor modifications of electrical system required
–
Electrical
AFP- Installation of 3 rows of 10' high storage racks to match existing. No modifications to electrical, mechanical, or plumbing systems.
–
Demolition
Demolish small building and cell tower located in the southeast portion of parcel; east of parking lot.
–
Fire systems
Replacement of fire panel in building 15-8
–
Alteration or repair
Relocate existing environmental services operations to buildings 15-8. 16/N.s.e., dunnage bay & storage of 1.4q materials in bldg 16. F-2/h-3 occupancy / IIB construction
–
Other
AFP: Permit to close out 49 expited permits issued to the TRW plant. Bld2003-01840, bld2003-02309, bld2003-03886, bld2004-03065, bld2005-07972, bld2005-11397, bld2005-12171…
–
Other
AFP: Create permit for closing out multiple exprired permits
–
Fire systems
Modify existing fire alarm system. Adding (2) pull stations, (1) monitor modules, (3) exp-proof heat detectors, (2) relay modules and (3) horn strobes
–
Electrical
TRW / AFP bld2007-01878-g0103 Project scope consists of the relocation of an existing "E-test" Station and the installation of a new Arc Stud Welder within the existing B15/G…
–
Alteration or repair
Installation of "ingiter sub-assy"line & inflator final assy" line b15/a and installatin of ingnition unit pre-assy" in b15/b2. No changes to fire sprinkler system.
–
Addition
AFP/TRW Addition of interior walls and ceiling assembly to create an equipment rooms for a CT Scanner in Building 15 Area G at TRW. Electrical and Mechanical systems to be…
–
Alteration or repair
Install new sp1-2 inflator welding stn. W/ exhaust, compressed air & elect. Power mods. And a manual load stn. Both in area b1 of bldg B ( h3/iib ) at trw site II. To include…
–
Electrical
AFP / TRW bld2007-01878-g0101 Bldg. 15 / Area `I? ? Environmental Testing Chambers Installation. 10 new environmental testing chambers to conduct thermal testing of inflators in…
–
Demolition
Repair of existing cmu wall by demolition and reconstruction. All new cmu to match existing.
–
Fire systems
Deferred fire alarm modifications in p-bay of bldg15 at trw site II. Ref bld2012-06100. To include: new chimney heat detectors and connection to existing fire alarm system.
–
Alteration or repair
Relocate existing igniter sub assembly line (195) from b15/p2 to b15/q. To include:modification of elect.power and lighting. W/ reduced hazardous mat'l quantities. To include…
–
Alteration or repair
Remodel bldg 15 - area c at trw site II ( h-2/b /iib ) relocating existing flexcell from bldg b14. Modify assembly line 3. To include: demo existing chiller units, pumps, piping…
–
Mechanical (HVAC)
AFP / TRW BLD2007-01878-0100 B15/I - Water Jet Installation" project for TRW / Site II; Installation of a new "Water Jet" machine w/ support equipment in existing room "I35" for…
–
Alteration or repair
Remodel 8,828 SQ FT of pre-final assembly area p1 for the installation of shi-2 final inflator assembly line#56 ( h3 IIB ) of bldg#15 at trw site II. To include: roof mtd exhaust…
–
Fire systems
Afp - trw / afp bld2007-01878-0099 bldg. 15 / Areas 'g', 'h' & 'm' interior improvements. AREA G - Interior improvements to accommodate a records room within the existing…
–
Alteration or repair
Remodel a portion of the 19,391 SQ FT of existing r.o.i. Inflator assembly/gas pad for 2 new lines , the igniiter assembly line#196 and the helium leak check line#197 in area q (…
–
Roofing
AFP - TRW # bld2007-01878-00 "Bldg. 15 / Area "D" - Inflator Assy. Room Ventilation Modifications" project for TRW / Site II. Permit includes the installation of a new…
–
Alteration or repair
2,460 SQ FT Remodel of area d2 ( h2 / IIB ) of bldg 15 at trw for igniter assembly use. Increasing 1.3q propellant quanities by 11.1 lbs. To include: install 1 new wet ruwac dust…
–
Mechanical (HVAC)
Remove existing smoke detectors from bldg. 15 Spine and replace with addressable beam smoke detectors detectors ( fsb-200s a ) single ended , reflector type at trw.
–
Mechanical (HVAC)
Modify fire alarm adding ( frm-1a & fcm-1 rel a ) ) control/relay and release modules and connect to fire shutters for new processes in m bay bldg 15 at trw. To include: wiring
–
Demolition
AFP - "Bldg. 15 Areas G & O 2007-01878-g0097 project for TRW / Site II Remodel existing men's and women's restrooms, including the installation of new plumbing fixtures, permit…
–
Alteration or repair
Code modification to use blast pressure resistant construction in place of separate bldg where quantites of hazardous materials exceed the maximum allowable quantities.
–
Alteration or repair
Code modification to allow div 1.3 materials stored of used in bldg in quantities exceeding the maximum allowable quantity per control area as indicated in table 307.7(1) 2006 ibc
–
Alteration or repair
13,451 SQ FT Remodel and change of occupancy of 15m for install di-10 propellant transfer/load and inflator assembly operations and associated supt equipment in bldg 15 ( h2 IIB )…
–
Mechanical (HVAC)
Code modification for bld2012-00054 to add indoor and mobile day boxes area p2 bldg-15 at trw site II
–
Mechanical (HVAC)
Add new compartmentalized fixed daybox & new mobile daybox in area p2 at trw bldg. 15 At site II. To include: new wall mtd. Barometric relief louver. See approved code…
–
Electrical
AFP - TRW / AFP bld2007-01878-g0096 Bldg.15 / Area 'Q' - SHI-2 Gas Fill Line Installation . Relocation of existing inflator body Assembly lines / equipment to south end of…
–
Alteration or repair
Relocate exist. Magazine 15p-1 to a new conc. Pedestal/foundation north of bldg. 15/M1 & 15/p adjacent to mag 15m-1 at trw site II. Ref permit bld2010-02323 and addenda 2 code…
–
Addition
AFP - TRW / AFP bld2007-01878-0093 (2of 2).1) The addition of a new 10'-0"w x 40'-0" conc. pad for storing inert items. 2) Remove & replace existing high piled storage racks in…
–
Demolition
Afp - trw / afp bld2007-01878-0092 bldg. 15 / Area 'Q. Demolition of existing assembly equipment, associated support equipment, associated mechanical and electrical services…
–
Alteration or repair
Transfer storing/staging operations at trw site II bldg 15, from mag 15/d 10 & 11 to mag 15/d 20 increasing div 1.3 quantities by 50 lbs for a new combined total of 76.4 lbs at…
–
Electrical
AFP - Bldg. 15 / Area 'I' - Module and Chemistry Lab Expansion" Project" for TRW / Site II.The scope of this submittal is meant to document field changes / modifications made…
–
Alteration or repair
Remodel area 15/d ( h2/h3 / IIB ) at trw/vssi site II. To include: demo of existing sub. Assembly line, and istallation of relocated flekcell lines from 15/a and install…
–
Electrical
Afp - trw / afp bld2007-01878-0091. Project scope consists of the installation of a new x-ray machine and assoc. support equipment to support existing production operations in the…
–
Demolition
Afp - trw / afp bld2007-01878-0092. Project consists of the demolition of all exist. process and assembly equipment, associated support equipment, associated mechanical and…
–
Fire systems
AFP bld2007-01878-0090 - Project scope consists of removing the existing high-speed deluge nozzle and infrared fire detection (IFD) sensor located inside the existing SHI blast…
–
Addition
Install 10 FT high workstation protection lexan enclosures around 2 existing ( guni 75 ) propellant dosing/loading stations 592 SQ FT & install 2 new separation valves on the…
–
Alteration or repair
Code mod. To install a protective enclosure ( indoor vent chamber )to isolate div. 1.3 Propellant in open use and increase quanties of propellant in bay "a" of bldg 15 in lieu of…
–
Alteration or repair
Expedited: 11,266 SQ FT remodel of bldg. 15 "A" site II ( h3/h4 IIB ) to modify the existing assembly line for vpa ignition canister/ cell 2 bowl feeder for the ppi-3 inflator. To…
–
Addition
Addenda to bld2010-o2323. Change construction of new compressor shed from site built to pre-engineered metal building. No change in building area or MP&E.
–
Alteration or repair
Remodel and expand existing production test lab facility. Work includes removing existing waste tank from open underground concrete pit under existing building roof line, filling…
–
Fire systems
AFP - "Bldg.15 / Area 'K' - Shipping / Receiving Relocation" project for TRW / Site II. 1. Relocation of the existing Flange Weld lines and assoc. support equipment from Bldg…
–
Addition
Code mod #3, ref. BLD2010-02323 - TRW AM&M A15P.O3 - APPROVED - Code Modification is to use a specially designed mobile daybox to bring explosive material into the final assembly…
–
Addition
Code mod #2, ref. BLD2010-02323 - TRW AM&M A15P.O2 - APPROVED - Code Modification is to use "INTERCEPTOR-QR" indoor explosion venting system to comply with the explosion control…
–
Addition
Code mod #1, ref. BLD2010-02323 - TRW AM&M A15P.O1 - APPROVED - Code Modification is to use blast/pressure resistant construction in place of a separate building as required per…
–
Addition
Code study; including 3 code modifications (see below), remodel and addition to existing building for installation of shi-2 inflator assembly line. Remodel existing 13,391 sq. ft…
–
New building
New acoustical enclosure around existing technician's cubicles inside existing Bldg. 16 / 'C1'.Existing Mechanical and Electrical services already in place will be modified to…
–
Electrical
Project scope consists of the construction of a new acoustical enclosure around existing technician's cubicles inside existing Bldg. 16 / 'C1'.Existing Mechanical and Electrical…
–
Other
AFP - Relocate cubes from the production floor to the mezzanine to free up some space in the bay.
–
Alteration or repair
AFP / TRW bld2007-01878-0087- Relocation of the existing manual "Diffuser Load Station" and installation of an automated "Diffuser Load Station" on Lines #2 & #3 of the DI-9…
–
Electrical
TRW / AFP bld2007-01878-0086 - Relocation and installation of existing assembly equipment used for inert inflator assembly operations from Bldg. 50 into "Bldg. 15 / Area 'B'…
–
Mechanical (HVAC)
Modification of exist fire alarm system and devices. Ref bld2009-04399
–
Alteration or repair
Addenda (delta 3 )to orig. Permit 2009-04399 & code study to substitute a prefabricated 60 x 72 gravity relief ventilator unit w/ backdraft damper for the exhaust penthouse…
–
Alteration or repair
Code study & relocation of ppi-3 assembly line w/ assoc support equipment from bldg to 17 to bldg 15c for filter & inflator assembly / guni-65/75 propellant staging/load /transfer…
–
Alteration or repair
Code mode ref. BLD2009-03828. Modify indoor magazine use of mobile daybox and quanities per sms report #0653-r1
–
Alteration or repair
Code mod ref. BLD2009-03828. To use exisitng 20lbs per SQ FT wall and roof construction per sms report #2028-r1
–
Alteration or repair
Relocate service & prototype propellant loading operations to bay 1 & 3 and protype teardown operations to bay 2 in bldg 15-l a seperate bldg. At trw site II per consolidation. (…
–
Alteration or repair
Afp - trw/afp2007-0187-0085. Interior improvements to accomodate an office area within an existing mfg space. Existing process equipment will be relocated from around the site to…
–
Alteration or repair
12,324 SQ FT Remodel/relocation of exist. Di-9 igniter sub-assembly line #2 & associated supt equipment from bld 38 to bld 15d ( areas d2 & d3) at trw site II. ( H2/h3 IIB )…
–
Alteration or repair
AFP - Questions contact Terri Wood @ 480-644-4542. Trw/afp bld2007-01878-g0084. Remodel of plant managers area.
–
Alteration or repair
Install 125 gal vertical above ground propane tank & provide connection to relocated 30k btu burner in cherokee bay 6 at bldg. 15 ( I ) at trw site II. Burner to be installed per…
–
Electrical
AFP -Questions contact Terri Wood @ 480-644-4542.TRW / AFP2007-01878-g0083 (2 of 2) Modifications to existing assembly lines #3 & #4 in Bldg. 17.Existing Mechanical and Electrical…
–
Electrical
AFP -Questions contact Terri Wood @ 480-644-4542.TRW / AFP2007-01878-g0083 (1 of 2) Modifications to existing assembly lines #3 & #4 in Bldg. 17.Existing Mechanical and Electrical…
–
Electrical
AFP - Questions contact Terri Wood @ 480-644-4542. Trw / afp bld2007-01878-g0082 2 of 2. Relocating existing lab and manufacturing equipment from Bld 50 to Bld 15 / Area I…
–
Electrical
AFP - Questions contact Terri Wood @ 480-644-4542. Trw / afp bld2007-01878-g0082 1 of 2. Relocating existing lab and manufacturing equipment from Bld 50 to Bld 15 / Area I…
–
Fire systems
AFP - Questions contact Terri Wood @ 480-644-4542. Trw / afp bld2007-01878-00080. Relocation of existing admin operations from bld 2 to the newly redesignated office area of Bld…
–
Alteration or repair
Annual Facilities Permit - Questions contact Terri Wood 6444542 TRW / AFP bld2007-01878-00080 Relocation of existing open & hard wall office space & conference room from Bldg. 2…
–
Other
Annual Facilities Permit TRW /AFP bld2007-01878-0079 Relocation of an exist. egress stair, an exist. fill port welder and an exist. compressed air filter rack; and the…
–
Alteration or repair
1.Removing the existing assembly lines in Bldg. 15/K. 2.Relocation of the existing Flange Weld Lines and assoc. support equip. from Bldg. 15/D to Bldg. 15/K. 3.Relocating the…
–
Alteration or repair
Relocate the d1-9 inflator line & support equipment from bldg 38 to bldg 15/d, includes 4 code modifications, see attached in documents.
–
Electrical
Annual Facilities Permit Questions contact Carl White (6443588)TRW / AFP No. bldg2007-01878-g0077 Project scope consists of modifying the existing DI-9 / Line #3 assembly line in…
–
Other
Assembly operations for flexcell lines utilizing energetic materials. Increasing hazardous material division 1.4 explosives. Equipment installed under permit 2008-09659
–
Alteration or repair
Annual Facilities Permit -- Question contact Carl White 6443588.The project scope consists of relocating Flexcell lines 1 & 2 from Bldg .17, and Flexcell lines 3 & 4 from Bldg. 15…
–
Other
Annual Facilities Permit -- Questions contact Carl White 6443588. Bldg 15 / Area B2 Service Bay
–
Other
Install of stud welder in warehouse area of bld # 50/fees based on # of inspections
–
Mechanical (HVAC)
Afp- scope includes interior improvements to existing admin blding to include demo of extisting walls and ceilings to accomodate newc training rms, computer lab, and health…
–
Alteration or repair
Afp- bld # 15/ area 1/ scope is remodel of existing process equipment rm to mro rm/ fees based on # of inspections/ contact carl white @ 3588 with questions
–
Other
Work order # 2086 /friction welder installation/fees based on # of inspections
–
Other
Service reconfiguration /scope of phase 1 is the reinstallation of laser weld equipment/fees based on # of inspections
–
Addition
REF: BLD2008-04723 -- Approved Code Modification to allow the amount of 1.3 explosives in Building 15 Area C load room exceed the maximum permitted per IBC TABLE 307.1(1) and to…
–
Addition
Remodel with new construction of an existing building for the installation of PPI3 production line. Includes Code Study and Code Modification (REF BLD2008-05102). See Case Notes…
–
Electrical
this project scope consists of installing a new concrete pad for a new elect ses, transformer and switch; terminating the existing elect service to blds 15-5 and 15-8 and…
–
Electrical
Bldg. 15 AREA D The project scope consists of: Reorienting the existing Flexcell Assembly Line. Installing a new Flexcell Assembly Line just south of the exist Flexcell inside the…
–
Alteration or repair
The project consist of the installation of automated propellant loading equipment to replace the existing manual propellant loading operation in BLDG. 15/ Area A and the expansion…
–
Electrical
The project scope consist of the installation of 2 new automated "shorting clip" bowl feeder stations to replace an existing manual-feed operation on the existing assembly line…
–
Alteration or repair
This is a combination of two projects G0062 area B and G0063 area C The project consists of the demo of all existing process and assembly equipment associated support equipment…
–
Grading
The project scope entails providing independent on-site grading and drainage and retention resulting from previously approved lot split and conditional uses permit (Zoning case…
–
Other
Afp - any questions regarding this permit contact chris hester x4506 or patrick ott x5093. Generator installation for building #4
–
Roofing
Bldg. 50 Glamtronics Welder Installation- The project scope entails the installation a glamtronics welder in the main assembly bay of Bldg. 50, and an exsiting roof-mounted…
–
Electrical
Bldg. 15/ Area J- Compressor Exchange. The project scope entails the removal and replacement of an existing air compressor with a new compressor in the "Existing Room" of bldg…
–
Electrical
Bldg. 2 Area Chiller Replacement. The project scope entails the installation of a new HVAC chiller unit in the north mechanical yard of Bldg. 2. Exsitng mechanical and electrical…
–
Electrical
Bldg. 50 Stud Welder Installation. The project scope entails the installation of a new stud welder on the main assembly floor of Bldg 50. The existing electrical system will be…
–
Electrical
Bldg. 15 Area "I" - "Liebert A/C Installation". The project scope entails the installation of a portable a/c unit in the office/ support area of Bldg. 15/Area "I". The existing…
–
Demolition
Bldg. 17 - GMF "16 Lane Cutter Demolition". The scope of work consist of the demolition of the existing "16 Lane Cutter" in the exit cutter room", high-pressure pump in the…
–
Alteration or repair
Bldg. 2 / Admin Executive Office Remodle. The work entials remodel of the existing office area of bldg. 2 that includes reconfiguration of partions, power and diffuser loacations…
–
Electrical
Bldg. 15 Area "M" - "Friction Welder". The project scope entails the installation of a friction welder previously permitted under permit bld2004-08424 but never installed in the…
–
Roofing
BLDG 15/ Area "Q" Burst Disk Welder Installation. The project scope entails the installation of a new Burst Disk Welder" with associated support equipment (control panel, chiller…
–
Alteration or repair
Bldg. 15 AREA "C" LOAD ROOM RECONFIGURATION The project consists of removal of 2 existing weld lines and associated support equipment and the installation of a new igniter…
–
Alteration or repair
BLDG.17 -GMF PPI-3 LINE MODIFICATION The project consist of the modification of existing #3 filter tube sub-assembly line in the existing assembly room of bldg. 17 to support the…
–
Demolition
Bldg. 51 Storage Rack Demolition. The project entails the removal of the existing high-piled storage racks in the existing warehouse area of Bldg. 51. The exisiting high piled…
–
Electrical
Bldg. 15 / Area "Q" Helium Booster Pump. The project scope entails the installation of 2 helium booster pumps with a chainlink shade structure on the existing concrete mechanical…
–
Other
Code study lot split code summary. Verification of new allowable quantity distance for explosive storage based on new east property line resulting from lot split.
–
Other
BLDG 15 / Area M Equipment Installation. The work order for the project is 2086. The AFP project # is AFP- 00038 and the expiration date is 12/6/07
–
Roofing
Production line changes. Remove existing module assembly line and install ROI Inflator line #7. Disconnect existing utilities and reuse for new line. Install new fume exhaust…
–
Other
Bldg. 15 - Area "Q" Pencil tank Installation. The work order # for this project is 2086. The AFP project # is AFP-00038 and the expiration 12/6/07.
–
Addition
Assembly line change out only, no change in use, occupancy or occupant load. Remove three obsolete inflator assembly lines and replace with one new inflator assembly line (ROI…
–
Other
Annual facilities permit-above address is main site. Remote site located at 4051 N higley rd. Effective 11/4/05-11/4/06
–
Other
Annual facilities permit-above address is main site. Remote site located at 4051 N higley rd. Effective 11/04/2004-11/04/2005.
–
Other
After hours inspection
–
Addition
Relocate welding equipment from bldg 15 area m to a. Increase 1.4 explosives in a area by 28.6 lbs for a total of 62.71 lbs. Relocate lova loading to existing operating bay #4 in…
–
Alteration or repair
Code study for the use of guni azm 327 propellant in production within existing bays and equipment.
–
Addition
C tucker - remove existing module assembly lines to make room in north end of area "n" to install "roi" assembly line. Work includes modifying/relocating electrical. Plumbing and…
–
Other
Trw vssi mesa - code study for using guni azm-327 in bldg 15 area d. Amount in use outside of chimneys is below the maximum allowable quantities.
–
Addition
Install additional laser chiller and revise allowable area calcs. Install 3rd chiller and tie into existing laser chilled water loop. Install new breakes in dsp and install…
–
Alteration or repair
Code study to increase existing amounts of hazardous materials in dayboxes for production. Dayboxes(magazines) are associated with building 38.
–
Alteration or repair
Referance prj2003-00071 - code study for bld2003-01840: installation of hybrid gas inflator assembly line in bays 4 and 5 of existing building 50.
–
Other
Code study for bld2003-03886, ref prj2003-00070
–
Addition
Prj2003-00070 - relocation of drivers side canister igniter loading di-1/di-2 operation sqft. From site 1 to bldg.15 "b" generate load room, 2,348 sqft. For trw vehicle safety.to…
–
Other
Annual facilities permit - main site
–
Alteration or repair
Install pole mtd, light fixture near mag. 17A. Connect to existing light circuit
–
Demolition
Selective equipment demolition/removal -- demo permit only -- note: existing fire alarm and fire protection systems to be protected and remain operational during work. -- Work…
–
Addition
Referance prj2003-00071 & code study bld2003-04457 - project includes the installation of hybrid gas inflator assembly line in bays 4 and 5 of existing building 50. Work includes…
–
Alteration or repair
Relocate ball mill, oven, glove box and scale for propellant test preperation from building 16-h (test lab) to room 147 building 55-1
–
Alteration or repair
Relocate stud welder from area "g" to area "a" with all associated utilities. existing div.1.4 hazardous material quantities previously permitted #233287 will be increased by…
–

More permits in ZIP 85212